FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1080
Activity #: 21528.1208.01
Capital Project Title: Point of Rocks WWTP Renovation
Region: Brunswick
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2023 Est Completion Date: 6/30/2025
Capital Project Description: Renovation of existing Point of Rocks Wastewater Treatment Plant
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Architect/Engineering
750,000
500,000 250,000
Construction - County Funded 3,600,000
3,600,000
Inspectors - County Project Management
360,000 600,000 600,000
360,000
300,000 300,000 300,000 300,000 1,100,000 4,810,000
Overhead
Total Cost:
5,910,000
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
3,505,000 2,405,000 5,910,000
1,100,000 2,405,000
2,405,000
Total Cost:
1,100,000 4,810,000