FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1061
Activity #: 21454.1217.01
Capital Project Title: Crestview WWTP Improvements
Region: Frederick
Capital Project Status: In Progress Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2021 Est Completion Date: 10/6/2023
Capital Project Description: Project includes the design, construction, and inspection services required to install a pre-packaged WWTP at the existing Crestview plant site. This new 36,000 gpd (average day) SBR plant will either serve as a second treatment train or as the primary plant with reuse of the existing plant to provide operational redundancy.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Architect/Engineering 148,100 148,100 Construction - County Funded 6,450,800 1,686,904 4,763,896 Inspectors - County 163,000 163,000 Project Management 31,100 31,100 Overhead 81,500 81,500 Total Cost: 6,874,500 2,110,604 4,763,896
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
667,276 667,276
6,207,224 1,443,328 4,763,896 6,874,500 2,110,604 4,763,896
Total Cost: