FY2024-FY2029 Adopted Capital Improvement Program

FY2024 - 2029 Adopted Capital Improvement Program Highways - Continued

Project

2026

2027

2028

2029

Costs After

Pavement Management Program Highway Network Systemic - General Sidewalk Retrofit Program Pedestrian and Bicycle Missing Links Traffic Control and Safety Cloverhill Stormdrain Improvements Drainage Assessment Response Team (DART) Thurmont & Johnsville Satellite Facility Improvements

13,688,415 2,195,700

20,188,415 2,195,700

23,188,415 2,195,700

21,185,415 2,195,700

0 0 0 0 0 0 0 0

0 0

0 0 0 0

0 0 0 0 0

0 0 0 0 0 0 0

189,800

189,800

189,800

189,800

0

946,870

0

6,603,818

Frederick Satellite Yard Intercoastal Drive Brine System

0 0

0 0

892,983

8,022,338

0

0

Total Expense

17,020,785

29,177,733

26,466,898

23,570,915

8,022,338

Funding General Fund

10,472,670 6,548,115

10,950,800 18,226,933

8,604,300 17,862,598

9,047,300 14,523,615

0

General Fund Bonds & Capital Leases

8,022,338

Other

0

0

0

0

0

Total Funding Sources

17,020,785

29,177,733

26,466,898

23,570,915

8,022,338

171