FY2024-FY2029 Adopted Capital Improvement Program

Capital Project Summary

Capital Project Number: RD1064 Capital Project Title: Yeagertown Road

Activity #:

Region: New Market

Asset Type: Roads Asset Category: Roads

Year Identified: 2010 Est Completion Date: 12/15/2029

Capital Project Status: Active

Capital Project Description: This roadway serves as a link from Boyers Mill Road to the proposed I-70/Meadow Road Interchange/Ijamsville Road. The project will upgrade the existing tar and chip road to a modified minor arterial from Boyers Mill Road for approximately 0.7 miles. The remaining 1.1 miles to Old National Pike will be upgraded to a local road status. Replacement of existing Bridge No. F09-06 will likely be required as part of the project. The project will upgrade the existing tar and chip surface and serve future traffic growth. The 2022 ADT is 3,203 vehicles per day.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2024

2025

2026

2027

2028

2029 Costs After

Studies / Surveys

410,000

410,000

Land

1,858,900

1,858,900

Site Improvement - NonBldg

452,300

452,300

Architect/Engineering

1,147,500 8,490,300

977,700

169,800

Construction

8,490,300

Inspectors - County Project Management

725,400 284,100

725,400

284,100

Total Cost:

13,368,500

694,100 977,700 2,311,200

9,385,500

Funding Schedule:

Project Total

Prior Budget

Categories

2024

2025

2026

2027

2028

2029 Costs After

Trans from General Fund General Obligation Bonds

7,763,054 5,605,446 13,368,500

64,700

95,754 303,200

7,299,400 2,086,100 9,385,500

629,400 881,946 2,008,000 694,100 977,700 2,311,200

Total Cost:

133