Capital Project Number: GG3090
Activity #: C4050.4050.01
Capital Project Title: Integrated Library System Migration
Region: Countywide
Asset Type: Library Asset Category: General Government
Year Identified: 2020 Est Completion Date: 6/30/2022
Capital Project Status: Active
Capital Project Description: FCPL's contract for its Integrated Library System ends December 31, 2021. The Department is looking at a possible migration to a new vendor at that time. In addition to a software migration, the hardware associated will need to be replaced as it is nearing end of life, is not PCI compliant, and will not be compatible with an upgrade in software. CIP Request: to Replace Integrated Library System (update 2020 with new funding amounts) Description/Justification: FCPL's contract for its Integrated Library System ends on December 31, 2021. The Department is looking at a possible migration to a new vendor at that time. In addition to software migration, the hardware associated will need to be replaced as it is nearing the end of life, is not PCI compliant, and will not be compatible with an upgrade in software. An increased amount of funding is being requested for FY22 based on an increase in the cost to replace hardware.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Capital - Software
185,000 300,000 485,000
75,000 110,000
Capital - IIT Hardware
300,000
Total Cost:
75,000 410,000
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Trans from General Fund General Obligation Bonds
185,000 300,000 485,000
75,000 110,000
300,000
Total Cost:
75,000 410,000