FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG3007
Activity #:
Capital Project Title: West Frederick Library Study/Design
Region: Frederick
Asset Type: Library Asset Category: General Government
Year Identified: 2021 Est Completion Date: 12/1/2028
Capital Project Status: Active
Capital Project Description: This project constructs a building with 15,000 s.f. of space for a library branch with the exact location along or near Route 40 to be determined. It will provide library service to the West and North side of Frederick City, an area currently served by two bookmobile stops (Hillcrest and Waverly).
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Studies / Surveys
200,000 642,418 30,650 873,068
200,000
Architect/Engineering Project Management
642,418 30,650 673,068
Total Cost:
200,000
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
State Grants - Capital Trans from General Fund General Obligation Bonds
320,000 200,000 353,068 873,068
320,000
200,000
353,068 673,068
Total Cost:
200,000
81