FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG3006
Activity #:
Capital Project Title: Linganore Town Center Library
Region: New Market
Asset Type: Library Asset Category: General Government
Year Identified: 2017 Est Completion Date: 12/1/2027
Capital Project Status: Active
Capital Project Description: This project constructs a single-story 25,000 s.f. library off MD RT 144, convenient to the Oakdale Elementary School. It will provide library service to Spring Ridge, Lake Linganore, New Market, and Monrovia, areas currently without library service.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Site Improvement - NonBldg
24,166 990,811
24,166 990,811
Architect/Engineering
Construction
9,908,108
9,908,108
Construction - IIT Infrastruct
96,423 157,080 58,978
96,423 157,080 28,770
Inspectors - County Project Management
30,208
Capital - Furniture / Equipmen 2,885,586
2,885,586
Capital - IIT Hardware
68,451
68,451
Total Cost:
14,189,603
1,045,185 10,258,832 2,885,586
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
State Grants - Capital Trans from Impact Fee General Obligation Bonds
3,800,000 3,145,185 4,244,418 3,000,000 14,189,603
400,000 2,000,000 1,400,000 645,185 2,000,000 500,000
3,258,832 985,586
Impact Fee Bonds
3,000,000
Total Cost:
1,045,185 10,258,832 2,885,586