FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG2043
Activity #:
Capital Project Title: Montevue Campus 911 Center Expansion
Region: Frederick
Asset Type: Public Safety Asset Category: General Government
Year Identified: 2021 Est Completion Date: 12/31/2028
Capital Project Status: Active
Capital Project Description: A Space Needs Assessment was completed in 2020, which identified various Frederick County agencies' requirements for additional space. The Assessment evaluated the agencies' space requirements based on a ten-year projection. Two agencies that require immediate attention are Emergency Management and IIT. This project will include an addition to the existing Backup 911 Center on the Montevue Campus. This two-story expansion, of approximately 35,000 square feet, will include additional space for Emergency Management and IIT. The additional space requirements are consistent with the Space Needs Assessment report. Additional parking will also be included in the project.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Site Improvement - NonBldg
100,000
100,000
Architect/Engineering
1,759,500 17,595,500 1,125,000
1,759,500
Construction
17,595,500 1,125,000
Construction - IIT Infrastruct
Inspectors - County Project Management
140,000 50,000
140,000 25,000
25,000
Capital - Furniture / Equipmen 1,759,500
1,759,500
Capital - IIT Hardware
125,000
125,000
Total Cost:
22,654,500
1,884,500 20,770,000
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After 1,884,500 20,770,000 1,884,500 20,770,000
General Obligation Bonds
22,654,500 22,654,500
Total Cost: