FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1068
Activity #:
Capital Project Title: Green Valley FD Sewerline Extension
Region: New Market
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2021 Est Completion Date: 11/30/2022
Capital Project Description: Project includes the construction of approximately 4,700 LF of low pressure sewer main and appurtenances from the station site, along Fingerboard Road and Ed McClain Road, to the existing gravity sewer at Starling Alley. Project is funded by the General Government CIP.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Construction - County Funded
633,000 69,000 25,500 34,500 762,000
633,000 69,000 25,500 34,500 762,000
Inspectors - County Project Management
Overhead
Total Cost:
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Trans from Capital Project Fund
762,000
762,000
Total Cost:
762,000
762,000