FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: HW3004
Activity #: C6780.6780.01
Capital Project Title: Roads Satellite Facilities #3
Region: Middletown
Asset Type: Highway Asset Category: Highways
Year Identified: 2010 Est Completion Date: 4/1/2022
Capital Project Status: In Progress
Capital Project Description: This project enables the County to station staff, materials, and equipment at the Myersville and Jefferson satellite facilities. Myersville improvements include the remediation of water well deficiencies, a new entrance onto U.S. 40, truck shed with wash bay, brine system, pre-engineered building requisite for 24/7 operation, fuel island and back-up generator, renovation of the welding shop, and security features. Fuel storage, a generator, truck shed with wash bay, brine system, and security features are provided at Jefferson.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
NonCapital Furniture / Equipment
20,400
10,200
10,200
Site Improvement - NonBldg
249,941 166,627 441,750 416,750
83,314 25,000
Architect/Engineering
Construction
6,821,615 4,898,281 1,923,334
Construction - IIT Infrastruct
50,385
33,590
16,795 50,000 20,000 15,810 23,590
Inspectors - County Project Management
301,715 251,715 137,924 117,924
Capital - Furniture / Equipmen
47,430 70,769
31,620 47,179
Capital - IIT Hardware
Total Cost:
8,141,929 5,973,886 2,168,043
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Trans from General Fund General Obligation Bonds
101,936 101,936
8,039,993 5,871,950 2,168,043 8,141,929 5,973,886 2,168,043
Total Cost: