FY2022-FY2027 Adopted Capital Improvement Program
FY2022 - 2027 Adopted Capital Improvement Program Highways
Project
6-year
Total Project
Prior
2022
2023
Pavement Management Program Highway Network Systemic - General
105,386,000 105,386,000
0
17,414,600 1,205,000 1,365,700 369,300 154,000 263,938 512,500
15,892,000 1,205,000 1,365,700
7,230,000 5,462,800 369,300 924,000 263,938 3,587,500 5,847,995 2,168,043 725,000 330,686 527,875
8,575,162 12,350,631 879,600 924,000 763,938 3,837,500 5,847,995 8,141,929 7,238,222 330,686 1,042,875
1,345,162 6,887,831 510,300
Sidewalk Retrofit Program Sidewalk Missing Links Traffic Control and Safety
0
0
154,000
Cloverhill Stormdrain Improvements Drainage Assessment Response Team (DART) Thurmont & Johnsville Satellite Facility Improvements Roads Satellite Facilities #3 Frederick Satellite Yard Intercoastal Drive Brine System Highway Operations Satellite Facility Acquisition
500,000 250,000
0
768,750
0
0
0
5,973,886
2,168,043
0 0 0 0
0 0
0
330,686 527,875
515,000
Total Expense
132,823,137 155,318,538
15,982,179
24,311,642
19,385,450
Funding General Fund
58,370,000 74,453,137
60,406,900 94,911,638
2,036,900 13,945,279 15,982,179
6,402,500 17,909,142 24,311,642
11,649,650 7,735,800 19,385,450
General Fund Bonds & Capital Lease
Total Funding Sources
132,823,137 155,318,538
156