FY2022-FY2027 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: RD1068
Activity #: C6308.6308.01
Capital Project Title: Christopher's Crossing Widening
Region: Frederick
Asset Type: Roads Asset Category: Roads
Year Identified: 2016 Est Completion Date: 12/15/2023
Capital Project Status: In Progress
Capital Project Description: This project will include improvements to Christopher's Crossing from Whittier Drive (City Limit) to the Walter Martz Road/Jordan Valley Way intersection to upgrade from a two-lane median divided roadway to a four-lane median divided roadway. Upgrade of this roadway is necessary to provide a roadway typical section consistent with the adjoining Frederick City maintained segments of Christopher's Crossing. This upgrade is also necessary to accommodate the increased traffic anticipated with completion of the US 15/Monocacy Boulevard interchange by SHA and completion of missing segment between the Walter Martz/Poole Jones and Opposomtown Pike intersections by Frederick City. Intersection improvements at the Christopher's Crossing/Yellow Springs intersection may include the addition of a second lane to the existing roundabout. This road is designated as an on-street bikeway. The 2015 ADT on this roadway is 4,618 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Land
250,000 75,500
250,000 75,500
Site Improvement - NonBldg
Architect/Engineering
799,900 799,900
Construction
5,611,000
5,611,000
Inspectors - County Project Management
336,800
336,800
213,100 213,100
Total Cost:
7,286,300 1,013,000 325,500 5,947,800
Funding Schedule:
Project Total
Prior Budget
Categories
2022
2023
2024
2025
2026
2027 Costs After
Trans from General Fund General Obligation Bonds
373,800
34,100
2,200 337,500
6,912,500 978,900 323,300 5,610,300 7,286,300 1,013,000 325,500 5,947,800
Total Cost: