FY2022-FY2027 Adopted Capital Improvement Program

Capital Project Summary

Capital Project Number: RD1068

Activity #: C6308.6308.01

Capital Project Title: Christopher's Crossing Widening

Region: Frederick

Asset Type: Roads Asset Category: Roads

Year Identified: 2016 Est Completion Date: 12/15/2023

Capital Project Status: In Progress

Capital Project Description: This project will include improvements to Christopher's Crossing from Whittier Drive (City Limit) to the Walter Martz Road/Jordan Valley Way intersection to upgrade from a two-lane median divided roadway to a four-lane median divided roadway. Upgrade of this roadway is necessary to provide a roadway typical section consistent with the adjoining Frederick City maintained segments of Christopher's Crossing. This upgrade is also necessary to accommodate the increased traffic anticipated with completion of the US 15/Monocacy Boulevard interchange by SHA and completion of missing segment between the Walter Martz/Poole Jones and Opposomtown Pike intersections by Frederick City. Intersection improvements at the Christopher's Crossing/Yellow Springs intersection may include the addition of a second lane to the existing roundabout. This road is designated as an on-street bikeway. The 2015 ADT on this roadway is 4,618 vehicles per day.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2022

2023

2024

2025

2026

2027 Costs After

Land

250,000 75,500

250,000 75,500

Site Improvement - NonBldg

Architect/Engineering

799,900 799,900

Construction

5,611,000

5,611,000

Inspectors - County Project Management

336,800

336,800

213,100 213,100

Total Cost:

7,286,300 1,013,000 325,500 5,947,800

Funding Schedule:

Project Total

Prior Budget

Categories

2022

2023

2024

2025

2026

2027 Costs After

Trans from General Fund General Obligation Bonds

373,800

34,100

2,200 337,500

6,912,500 978,900 323,300 5,610,300 7,286,300 1,013,000 325,500 5,947,800

Total Cost:

132

Made with FlippingBook Digital Publishing Software