FY2022 - 2027 Adopted Capital Improvement Program Watershed Restoration & Retrofit - Continued
Project
2024
2025
2026
2027
Costs After
County-Owned Stormwater Facility Retrofits
732,917 929,284 1,794,419 4,237,069
0
0
0 0 0 0
0 0 0 0
Reforestation Program Stream Restorations
888,736 3,635,515 1,427,035
1,338,163
0
Non-County Owned Stormwater Facility Retrofits Cloverhill Stormwater Retrofits
1,410,368
0 0
0
0
0
0
Watershed Systemics
929,237
4,565,700 7,314,231
6,662,500 6,662,500
6,947,759 6,947,759
Total Expense
7,693,689
6,880,523
Funding General Fund
180,000 7,513,689
876,927 6,003,596
3,424,275 3,889,956
4,996,875 1,665,625
6,037,500 910,259
General Fund Bonds & Capital Lease
Grants
0
0
0
0
0
Total Funding Sources
7,693,689
6,880,523
7,314,231
6,662,500
6,947,759