FY2021 Adopted Budget
Capital Project Summary
Capital Project Number: RD1067
Activity #: C6303.6303.01
Capital Project Title: Gas House Pike (from the City Limits to Boyers Mill Road)
Region: New Market
Asset Type: Roads Asset Category: Roads
Year Identified: 2013 Est Completion Date: 12/16/2022
Capital Project Status: In Progress
Capital Project Description: This project will upgrade Gas House Pike from the Frederick City Limit to Boyers Mill Road to serve future traffic growth in the New Market region. Gas House Pike will be designed and constructed to minor arterial standards, modified to provide 5-foot paved and 4-foot grass shoulders for a distance of about 2.7 miles. Other proposed improvements may include horizontal and vertical alignments, road widening, shoulder construction, and intersection improvements. The 2015 ADT ranges from 5,343 vehicles per day (west of Boyers Mill Road) to 6,895 vehicles per day (west of Linganore Road).
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2021
2022
2023
2024
2025
2026 Costs After
Studies / Surveys
268,000 268,000 2,187,000 1,547,000 878,600 853,000 1,344,200 1,344,200 9,640,800 467,000 740,500 192,000 15,059,100 4,671,200
Land
640,000 25,600
Site Improvement - NonBldg
Architect/Engineering
Construction
9,173,800
Inspectors - County
548,500
Total Cost:
10,387,900
Funding Schedule:
Project Total
Prior Budget
Categories
2021
2022
2023
2024
2025
2026 Costs After
State Grants - Capital Trans from General Fund General Obligation Bonds
900,000
900,000
2,680,200 223,400 11,478,900 4,447,800 15,059,100 4,671,200
2,456,800 7,031,100 10,387,900
Total Cost:
582