FY2021 Adopted Budget

Capital Project Summary

Capital Project Number: PR3001

Activity #: C7200.7200.01

Capital Project Title: Bikeways/Trails Program

Region: Countywide

Asset Type: Parks & Recreation Asset Category: Parks & Recreation

Year Identified: 2010 Est Completion Date: 12/1/2026

Capital Project Status: Active

Capital Project Description: The Frederick County Bikeways and Trail Plan updated in 2018 identified sites and areas to develop potential trail corridors in the County. In this CIP request, the County will be scheduling design and construction funding years from FY2021 to FY2026. Funding may be needed and used for potential trail acquisition, easements, and construction as needed. County Staff will also look at utilizing 80/20 matching grants from the Federal Transportation Alternatives Program (TAP) and Maryland Bikeways Grant Program for eligible trail projects.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2021

2022

2023

2024

2025

2026 Costs After

Architect/Engineering

1,413,654 427,454 221,200 154,500 235,500 178,500 196,500

Construction

8,841,333

1,733,333 2,008,000 1,030,000 1,570,000 1,190,000 1,310,000

Inspectors - County Project Management

505,127 195,233

21,911 11,903

80,536 30,650

80,536 30,365

80,536 30,650

80,536 30,650

80,536 30,650

80,536 30,365

Total Cost:

10,955,347 461,268 2,065,719 2,273,401 1,376,686 1,859,686 1,497,686 1,420,901

Funding Schedule:

Project Total

Prior Budget

Categories

2021

2022

2023

2024

2025

2026 Costs After

Federal Grants - Capital Trans from General Fund Trans from Parks Acquisition General Obligation Bonds

6,325,477 136,544 1,213,333 1,405,600 721,000 1,099,000 833,000 917,000

7,280

7,280

4,588,776 283,630 852,386 867,801 655,686 760,686 664,686 503,901

33,814

33,814

Total Cost:

10,955,347 461,268 2,065,719 2,273,401 1,376,686 1,859,686 1,497,686 1,420,901